Aris Mining Increases Segovia Gold Mineral Reserves By +75% To 1.3 Moz, Announces Plant Expansion To Increase Production Rate
Aris Mining is also increasing the capacity of the Maria Dama processing plant within the Segovia Operations from 2,000 to 3,000 tonnes per day (tpd). As we have an existing unutilized ball mill on site, the costs for the plant expansion are estimated at $11.0 million and completion is expected by early 2025.