• Live Feeds
    • Press Releases
    • Insider Trading
    • FDA Approvals
    • Analyst Ratings
    • Insider Trading
    • SEC filings
    • Market insights
  • Analyst Ratings
  • Alerts
  • Subscriptions
  • Settings
  • RSS Feeds
Quantisnow Logo
  • Live Feeds
    • Press Releases
    • Insider Trading
    • FDA Approvals
    • Analyst Ratings
    • Insider Trading
    • SEC filings
    • Market insights
  • Analyst Ratings
  • Alerts
  • Subscriptions
  • Settings
  • RSS Feeds
PublishGo to App
    Quantisnow Logo

    © 2026 quantisnow.com
    Democratizing insights since 2022

    Services
    Live news feedsRSS FeedsAlertsPublish with Us
    Company
    AboutQuantisnow PlusContactJobsAI superconnector for talent & startupsNEWLLM Arena
    Legal
    Terms of usePrivacy policyCookie policy

    Endeavour Silver provides a Q3 2024 construction progress update on Terronera; the surface construction progress has reached 77% completion

    10/21/24 6:50:00 AM ET
    $EXK
    Precious Metals
    Basic Materials
    Get the next $EXK alert in real time by email

    VANCOUVER, British Columbia, Oct. 21, 2024 (GLOBE NEWSWIRE) -- Endeavour Silver Corp. ("Endeavour" or the "Company") (NYSE:EXK, TSX:EDR) is pleased to provide a Q3 2024 construction progress update for its Terronera Project in Jalisco state, Mexico. A photo gallery presentation accompanies this news release and can be found here or on the Company website at Terronera Project Progress Photos. All dollar ($) references in this news release are in United States dollars.

    The Terronera project made substantial progress during the third quarter as the Upper Plant Platform nears completion. Surface mill and infrastructure construction reached 90%, further preparing for advancement into operations. Focus continues on the Lower Platform, where concrete work is well underway, and the Tailing Storage Facility, with underdrain embankment fill and pipe installation advancing at a good pace.

    "We're in the final construction phase with the finish line in sight," commented Don Gray, Chief Operating Officer. "The Upper Platform is nearly complete, and the primary jaw crusher was commissioned, with rock crushed in August. The major focus is the Lower Platform and Tailing Storage Facility. Our dedicated Terronera team continues to meet the challenges both for developing the mine and constructing the mill facilities to keep the project on track to begin commissioning systems near the end of Q4."

    Q3 2024 Construction and Development Highlights

    As of September 30, 2024, site works and activities included:

    • Safety – Health and safety for operational readiness is underway. The mine rescue equipment arrived, and team members are being recruited and trained. Two refuge stations were installed.
    • Community Relations – Local community support continues to be a priority. In Q3, the Company supported a series of local initiatives and investments such as: a municipal cooperative agreement; inauguration of an early-childhood development center; scholarships for university students in Santiago de Pinos; municipal road maintenance; workshops for business entrepreneurship for local residents; environmental education program for primary schools; community tree donation; and summer community workshops for children and youth.
    • Progress – Overall project progress (mine development and surface construction) reached 77% completion, with more than $258 million1 of the project's budget spent to date. Project commitments total $270 million1,2, 99% of the $271 million capital budget.



    • Mine Development – During the third quarter, 1,051 metres were developed underground for a project total of 5,544 metres. Furthermore:



      • Underground explosive magazines were completed and the explosive use permit application was submitted for approval, which is anticipated in Q4 2024.



      • Terronera main sump and pump station excavation and support were completed.



      • Development was nearly complete for the test stope that will be used to verify stope design criteria including opening span widths, length and height as well as establishing longhole drilling, blasting and backfill procedures.



      • Development ore was stockpiled on surface.



      • Slashing of an existing portal commenced for access to mine the high-gold grade La Luz vein, which is anticipated to be reached in H1 2025.

    • Upper Plant Platform Site – Mill and surface infrastructure construction was 90% complete and continues to transition to operations.



      • Primary Crusher – Primary jaw crusher was commissioned with rock crushed in August, marking a major project milestone.



      • Coarse Ore Stockpile and Reclaim ("COS") Tunnel – Reached 100% completion and pre-commissioning tests commenced.



      • Grinding and Thickening – Piping, mechanical, electrical, and instrumentation are expected to be completed in October.



      • Flotation – Compressor pressure vessel and air dryer systems were installed with piping connections in progress. Flotation equipment, including blowers, instrument, and valve installations are ongoing and scheduled for Q4 completion.



      • Raw and Process Water Tanks – Steel rings are in place and welding was over 90% complete. Inlet, outlet and access port installations, final weld testing, sand blast/mechanical cleaning, and painting are scheduled for completion in Q4.



    • Lower Facilities Platform and Tailing Storage Facility (TSF) – Lower Platform area was nearly 30% complete. Focus has been on completing the last section of the tailing filter bearing wall prior to starting the filter support deck; the first structural steel columns and beams were erected for the Concentration Filter building and equipment mechanical structures.



      • Main Embankment TSF – Excavation for the main embankment key trench was 100% complete, the secondary key was at 40% complete, and underdrain piping placement has been completed.



      • Tailing Filtration Area – More than 75% of the floor slab and 100% of the filter bearing wall for the tailing filter building has been poured. The tailing filters, which are stored at the Puerto Vallarta warehouse, are schedule to be transported to site for Q4 2024 installation.



      • Concentrate Filter Area – More than 80% of the floor slab and 75% of the pipe rack and equipment foundations in the concentrate filter area has been poured, and tank foundations and equipment pedestals were nearly complete.

    • Auxiliary Buildings – Laboratory and Plant Maintenance buildings reached 40% of completion.



      • Laboratory Building – Majority of the sheathing and insulation have been installed and steel studs are in place. Sheetrock and compressor and dryer installations are in progress.



      • Plant Maintenance Building – Structural steel installation started in late September.

    • Procurement –The project team continues to expedite pending arrivals. Procurement was 99% complete.



    • Onsite Personnel – At the end of Q3, the workforce increased to over 250 Endeavour Silver employees and over 800 contract workers, with the total number expected to decrease in Q4 2024 as commissioning begins.

    Next Steps and Planning

    The Terronera Project is tracking to begin commissioning systems near the end of Q4.

    For Q4 2024, the tailing filter area, which was turned over to the mechanical contractor in early October, will allow focus on installing at least one tailing filter along with the concentrate filter using an extended work schedule to allow initial systems commissioning anticipated near the end of Q4. Grinding, flotation, and thickening systems will be mechanically completed in late October, allowing testing and ramp-up of these circuits to begin in November and December.

    Mine development in Portals 1, 2, and 4 declines will continue, with longhole stopes being developed and initial production planned for Q4; ore will continue to be stockpiled for mill ramp-up. At La Luz, the portal is being constructed, and the orebody ramp access will advance in Q4.

    The critical path remains the TSF, tailing concentrate filters construction, and the advancing underground mine.

    Visit www.terronera.com, our dedicated project website, to stay informed on the ongoing development at Terronera. Explore updates, learn about our commitment to environmental stewardship, and discover the positive impacts on local communities.

    About Endeavour Silver: Endeavour is a mid-tier precious metals company committed to sustainable and responsible mining practices. With operations in Mexico and the development of the new cornerstone mine in Jalisco State, the Company aims to contribute positively to the mining industry and the communities in which it operates. In addition, Endeavour has a portfolio of exploration projects in Mexico, Chile, and the United States, which has helped it achieve its goal of becoming a premier senior silver producer. 

    Contact Information



    Allison Pettit, Director of Investor Relations

    Tel: (604) 640 4804

    Email: [email protected]

    Website: www.edrsilver.com

    Follow Endeavour Silver on Facebook, X, Instagram and LinkedIn

    Cautionary Note Regarding Forward-Looking Statements

    This news release contains "forward-looking statements" within the meaning of the United States Private Securities Litigation Reform Act of 1995 and "forward-looking information" within applicable Canadian securities legislation. Such forward-looking statements and information herein include but are not limited to statements regarding the development and financing of the Terronera Project, including capital cost estimates, the anticipated timing of the project construction and commissioning, Terronera's forecasted operations, costs and expenditures, and the timing and results of various related activities. The Company does not intend to and does not assume any obligation to update forward-looking statements or information other than as required by applicable law.

    Forward-looking statements or information involve known and unknown risks, uncertainties, and other factors that may cause Endeavor's actual results, level of activity, production levels, performance, or achievements, and its operations to be materially different from those expressed or implied by such statements. Such factors include but are not limited changes in production and costs guidance; the ongoing effects of inflation and supply chain issues on mine economics; national and local governments, legislation, taxation, controls, regulations and political or economic developments in Canada, Chile, the USA and Mexico; financial risks due to precious metals prices; operating or technical difficulties in mineral exploration, development and mining activities; risks and hazards of mineral exploration, development and mining; the speculative nature of mineral exploration and development; risks in obtaining necessary licenses and permits; continued compliance with the project loan debt facility; the ongoing effects of inflation and supply chain issues on the Terronera Project economics; fluctuations in the prices of silver and gold, fluctuations in the currency markets (particularly the Mexican peso, Chilean peso, Canadian dollar and US dollar); and challenges to the Company's title to properties; as well as those factors described in the section "risk factors" contained in the Company's most recent form 40F/Annual Information Form filed with the SEC and Canadian securities regulatory authorities.

    Forward-looking statements are based on assumptions management believes to be reasonable, including but not limited to the continued operation of the Company's mining operations, no material adverse change in the market price of commodities forecasted Terronera mine economics as of 2024, mining operations will operate, and the mining products will be completed under management's expectations and achieve their stated production outcomes, and such other assumptions and factors as set out herein. Although the Company has attempted to identify important factors that could cause actual results to differ materially from those contained in forward-looking statements or information, other factors may cause results to be materially different from those anticipated, described, estimated, assessed, or intended. There can be no assurance that any forward-looking statements or information will be accurate, as actual results and future events could differ materially from those anticipated in such statements or information. Accordingly, readers should not place undue reliance on forward-looking statements or information.


    1 Financial figures are based on a preliminary estimate. Final unaudited figures will be released with the Q3 2024 financial statements on November 5, 2024.

    2 Project commitments include total project expenditures.



    Primary Logo

    Get the next $EXK alert in real time by email

    Crush Q1 2026 with the Best AI Superconnector

    Stay ahead of the competition with Standout.work - your AI-powered talent-to-startup matching platform.

    AI-Powered Inbox
    Context-aware email replies
    Strategic Decision Support
    Get Started with Standout.work

    Q&A

    New
    • What is the current progress of Endeavour Silver Corp. on the Terronera Project as of Q3 2024?

      Endeavour Silver Corp. is making significant progress on the Terronera Project, with the Upper Plant Platform nearing completion and surface mill construction at 90%.

    • How much of the budget has been spent on the Terronera Project so far?

      A total of $258 million has been spent on the project, which is 99% of the planned $271 million capital budget.

    • What milestone was achieved at the Terronera Project in Q3 2024?

      The primary jaw crusher has been commissioned, which is a significant milestone for the project.

    • What is the status of the Lower Platform and Tailing Storage Facility at the Terronera Project?

      Roof construction on the Lower Platform area is nearly 30% complete, and efforts are ongoing for the Tailing Storage Facility with significant concrete work in progress.

    • What are the upcoming plans for Endeavour Silver Corp. regarding the commissioning of the Terronera Project?

      The company plans to initiate system commissioning near the end of Q4 2024, focusing on the tailing filter area, concentrate filter, and ongoing mine development.

    Recent Analyst Ratings for
    $EXK

    DatePrice TargetRatingAnalyst
    11/3/2025Neutral → Sector Outperform
    CIBC
    3/21/2025Outperform
    Raymond James
    11/29/2024Buy
    TD Securities
    6/17/2024$6.00Outperform
    BMO Capital Markets
    1/9/2024Hold → Buy
    TD Securities
    3/22/2022Market Perform
    BMO Capital Markets
    3/11/2022$8.00 → $8.50Buy
    HC Wainwright & Co.
    11/10/2021$7.00 → $8.00Buy
    HC Wainwright & Co.
    More analyst ratings

    $EXK
    Analyst Ratings

    Analyst ratings in real time. Analyst ratings have a very high impact on the underlying stock. See them live in this feed.

    View All

    Endeavour Silver upgraded by CIBC

    CIBC upgraded Endeavour Silver from Neutral to Sector Outperform

    11/3/25 9:52:35 AM ET
    $EXK
    Precious Metals
    Basic Materials

    Raymond James initiated coverage on Endeavour Silver

    Raymond James initiated coverage of Endeavour Silver with a rating of Outperform

    3/21/25 8:10:54 AM ET
    $EXK
    Precious Metals
    Basic Materials

    TD Securities resumed coverage on Endeavour Silver

    TD Securities resumed coverage of Endeavour Silver with a rating of Buy

    11/29/24 7:44:37 AM ET
    $EXK
    Precious Metals
    Basic Materials

    $EXK
    SEC Filings

    View All

    Amendment: SEC Form 6-K/A filed by Endeavour Silver Corporation

    6-K/A - ENDEAVOUR SILVER CORP (0001277866) (Filer)

    1/16/26 3:34:18 PM ET
    $EXK
    Precious Metals
    Basic Materials

    SEC Form 6-K filed by Endeavour Silver Corporation

    6-K - ENDEAVOUR SILVER CORP (0001277866) (Filer)

    1/16/26 6:51:04 AM ET
    $EXK
    Precious Metals
    Basic Materials

    SEC Form 6-K filed by Endeavour Silver Corporation

    6-K - ENDEAVOUR SILVER CORP (0001277866) (Filer)

    1/15/26 5:21:05 PM ET
    $EXK
    Precious Metals
    Basic Materials

    $EXK
    Press Releases

    Fastest customizable press release news feed in the world

    View All

    UPDATE – Endeavour Silver Provides 2026 Guidance

    NOTE TO READER – The news release of Endeavour Silver Corp. dated January 16, 2026, (the "News Release") has been re-filed on SEDAR. The previously filed News Release had a typographical error on page 3 with respect to the AISC for Terronera. The consolidated AISC remains the same as the previously filed News Release. This news release replaces the previously filed News Release. VANCOUVER, British Columbia, Jan. 16, 2026 (GLOBE NEWSWIRE) -- Endeavour Silver Corp. ("Endeavour" or the "Company") (NYSE:EXK, TSX:EDR) announces its consolidated production and cost guidance for the Terronera, Guanaceví, and Kolpa mines, along with its capital and exploration budgets for 2026. All dollar amounts

    1/16/26 3:16:05 PM ET
    $EXK
    Precious Metals
    Basic Materials

    Endeavour Silver Provides 2026 Guidance

    VANCOUVER, British Columbia, Jan. 16, 2026 (GLOBE NEWSWIRE) -- Endeavour Silver Corp. ("Endeavour" or the "Company") (NYSE:EXK, TSX:EDR) announces its consolidated production and cost guidance for the Terronera, Guanaceví, and Kolpa mines, along with its capital and exploration budgets for 2026. All dollar amounts are in US dollars (US$) and ounces are troy ounces. 2026 Production and Cost Guidance Highlights In 2026, silver production from Terronera, Guanaceví, and Kolpa is projected to range between 8.3 and 8.9 million ounces (oz), while gold output from Terronera and Guanaceví is expected to range between 46,000 and 48,000 oz. Kolpa is anticipated to contribute significant base metal

    1/16/26 6:50:00 AM ET
    $EXK
    Precious Metals
    Basic Materials

    Endeavour Silver Completes Sale of Bolañitos Mine

    VANCOUVER, British Columbia, Jan. 15, 2026 (GLOBE NEWSWIRE) -- Endeavour Silver Corp. ("Endeavour" or the "Company") (NYSE:EXK, TSX:EDR) is pleased to announce the completion of the sale of the Bolañitos silver and gold mine (the "Bolañitos Mine") to Guanajuato Silver Company Ltd. ("Guanajuato Silver") (TSXV:GSVR) pursuant to a share purchase agreement (the "Agreement") previously announced on November 24, 2025 (the "Sale"). "The sale of the Bolañitos Mine marks an exciting milestone for Endeavour as we continue to focus our resources on our core silver assets and strategic growth," said Dan Dickson, Chief Executive Officer. "We are pleased that Guanajuato Silver is well-positioned to fu

    1/15/26 5:20:00 PM ET
    $EXK
    Precious Metals
    Basic Materials

    $EXK
    Financials

    Live finance-specific insights

    View All

    Endeavour Silver Produces 6,486,661 Oz Silver and 37,164 Oz Gold, for a total of 11.2 Million Silver Equivalent Oz in 2025

    VANCOUVER, British Columbia, Jan. 08, 2026 (GLOBE NEWSWIRE) -- Endeavour Silver Corp. ("Endeavour" or the "Company") (NYSE:EXK, TSX:EDR)  reports full year 2025 production of 6,486,661 silver ounces ("oz") and 37,164 gold oz, and in combination with base metal production, a silver equivalent ( 1) ("AgEq") production of 11.2 million oz. Fourth quarter 2025 production was 2,030,206 silver ounces, 13,785 gold oz, and AgEq production of 3.8 million oz. All dollar amounts are in US dollars ($). "Endeavour delivered another year of strong growth in 2025, highlighted by record silver equivalent production and the successful ramp-up at Terronera," commented Dan Dickson, Chief Executive Officer.

    1/8/26 6:50:00 AM ET
    $EXK
    Precious Metals
    Basic Materials

    Endeavour Silver Announces Q3 2025 Financial Results; Earnings Call at 10AM PDT (1PM EDT) Today

    VANCOUVER, British Columbia, Nov. 07, 2025 (GLOBE NEWSWIRE) -- Endeavour Silver Corp. ("Endeavour" or the "Company") (NYSE:EXK, TSX:EDR) announces its financial and operating results for the three and nine months ended September 30, 2025. All dollar amounts are in US dollars ($). "Endeavour Silver delivered a strong third quarter, highlighted by a significant increase in production and robust revenue growth," commented Dan Dickson, Chief Executive Officer. "With silver equivalent production up 88% year-over-year and operating cash flow more than doubling, we continue to demonstrate the strength of our mining operations and our team's commitment to operational excellence. With the recent a

    11/7/25 6:50:00 AM ET
    $EXK
    Precious Metals
    Basic Materials

    Endeavour Silver Produces 1,766,926 Oz Silver and 7,286 Oz Gold (3.0 Million Silver Equivalent Oz) in Q3 2025 and Provides an Update on Terronera

    VANCOUVER, British Columbia, Oct. 08, 2025 (GLOBE NEWSWIRE) -- Endeavour Silver Corp. ("Endeavour" or the "Company") (NYSE:EXK, TSX:EDR) reports third quarter 2025 production of 1,766,926 silver ounces (oz), 7,286 gold oz, and in combination with base metal production, a silver equivalent(1) ("AgEq") total production of 3.0 million oz. All dollar amounts are in US dollars ($). All production amounts exclude Terronera pre-operating production. "We are pleased to deliver another strong quarter, marked by consistent performance across our portfolio," said Dan Dickson, Chief Executive Officer. "Our legacy mines continue to provide steady results, Kolpa is meeting expectations and integrating

    10/8/25 6:50:00 AM ET
    $EXK
    Precious Metals
    Basic Materials

    $EXK
    Leadership Updates

    Live Leadership Updates

    View All

    Endeavour Silver Announces Appointment of Chief Financial Officer

    VANCOUVER, British Columbia, Dec. 05, 2023 (GLOBE NEWSWIRE) -- Endeavour Silver Corp. ("Endeavour" or the "Company") (TSX:EDR, NYSE:EXK) is pleased to announce the appointment of Elizabeth Senez as the Company's Chief Financial Officer ("CFO"), effective January 1, 2024. Ms. Senez brings over 20 years of extensive experience in accounting, corporate finance, and corporate treasury to her new role. Concurrent with Ms. Senez's appointment, Christine West, the current CFO, will be transitioning to retirement. Ms. West will step down as CFO but will continue to support the Company through a transition period and retain her position on the Board of Directors until her retirement, a testament

    12/5/23 6:50:00 AM ET
    $EXK
    Precious Metals
    Basic Materials

    Endeavour Silver Appoints Vice President, Operations

    VANCOUVER, British Columbia, June 14, 2023 (GLOBE NEWSWIRE) -- Endeavour Silver Corp. ("Endeavour" or the "Company") (NYSE:EXK, TSX:EDR) announces, effective today, the appointment of Greg Blaylock as the new Vice President, Operations to oversee the Company's underground mining operations in Mexico. Greg Blaylock is a senior mining executive who brings to Endeavour over 35 years' hands-on experience in mining operations, mine planning and project development as well as related executive and technical expertise. Greg is fluent in both English and Spanish. Dan Dickson, Endeavour CEO, commented, "I am pleased to welcome Greg Blaylock to the Endeavour management team. Greg brings a wealth o

    6/14/23 6:50:00 AM ET
    $EXK
    Precious Metals
    Basic Materials

    Endeavour Silver Appoints Rex McLennan as Chairman

    VANCOUVER, British Columbia, Aug. 29, 2022 (GLOBE NEWSWIRE) -- Endeavour Silver Corp. ("Endeavour" or the "Company") (NYSE:EXK, TSX:EDR) announces that its Board of Directors (the "Board") has appointed the Company's Lead Director, Rex McLennan, as Chairman of the Board. Mr. McLennan steps into the Chairman position to replace former Executive Chairman, Bradford Cooke, who passed away suddenly and unexpectedly last week (see news releases dated August 18 and August 24, 2022). Rex McLennan joined the Company as an Independent Director in June 2007, appointed as Chair of the Audit Committee. As an Independent Corporate Director, he has chaired the audit committees of a number of publicl

    8/29/22 6:50:00 AM ET
    $EXK
    Precious Metals
    Basic Materials

    $EXK
    Large Ownership Changes

    This live feed shows all institutional transactions in real time.

    View All

    Amendment: SEC Form SC 13G/A filed by Endeavour Silver Corporation

    SC 13G/A - ENDEAVOUR SILVER CORP (0001277866) (Subject)

    10/8/24 11:51:00 AM ET
    $EXK
    Precious Metals
    Basic Materials

    SEC Form SC 13G/A filed by Endeavour Silver Corporation (Amendment)

    SC 13G/A - ENDEAVOUR SILVER CORP (0001277866) (Subject)

    2/14/23 11:57:02 AM ET
    $EXK
    Precious Metals
    Basic Materials

    SEC Form SC 13G/A filed by Endeavour Silver Corporation (Amendment)

    SC 13G/A - ENDEAVOUR SILVER CORP (0001277866) (Subject)

    2/11/22 11:48:56 AM ET
    $EXK
    Precious Metals
    Basic Materials